Summary

Size:
2,500
Type:
Museum
Budget:
$205,507
Date Completed:
06/24/2001

Description

•  Originally built in the 1940’s as a community school house
•  All wood frame construction with ship-lap wood siding
•  2,500 square foot school house was to retain all of the original construction to meet the requirements for registration as an historic landmark, while making the building weather-tight to accommodate an air-conditioning system and to meet current life safety code requirements for a fire sprinkler and fire alarm systems and to make provisions for handicap accessibility
MEP was design-build.
•  Site work involved fill and grading to establish historical relationship of building to surrounding grades.