Summary
- Size:
- 50,000
- Type:
- Education
- Budget:
- $4,080,000
- Date Completed:
- 08/01/1997
Description
• Two phased project
Phase 1: Two story new technical / vocational center that included nursing, dental, and culinary arts program
Phase 2: Main building renovation and new construction of classrooms
• Project fast tracked - December 1996 new building construction started; completed on schedule, August of 1997; renovation of existing classrooms started in June 1997 and was completed on schedule, August 1997