Mobilized a team to drill 75 holes at 3am and fill the voids with a urethane injection under taxiway
All work was done at night after last departure and the taxiway had to be open for traffic by the next mornings first departure
We returned 2 weeks later, milled the surface asphalt and repaved the entire area during the night