Summary

Size:
175,417
Type:
Education
Budget:
$15,502,000

Description

• Fast-track construction

• OAK was selected CM in March of 1999

• Construction started the last week of July

• Classes started in August 2000, full cafeteria service in November, and full completion was achieved in January 2001

• Two-story middle school classrooms connected with all other campus buildings by a fully enclosed mall with clerestory